Recently, Kaidi Biomass Power Generation's biomass generation project contracted to be built by Xinyuan electric Power Installation Company subordinating Anhui Nanling power supply company has sent out the 35 kV line across the board to start the construction.
The line is from Kaidi biomass power plant to the 220 KV Shengqiao transformer substation, and electricity from the power plant is transported through this rail to the substation Shengqiao and get connected to the grid. This rail line has 35 base line towers, about 4.5 km's length. They strive to complete construction work by April 15.