The "Wind power system technical requirements" is to be implemented in June this year, besides, the National Energy Bureau published the "distributed access wind power project development and construction guidance". It is easy to find out that China has made great efforts in the management of wind power grid-connection, and the attitude is becoming more resolute.
However, it seems that the two measures by the authorities did not get the full support of the industry and investors.
In the opinion of the majority of industry insiders, "Wind power system technical requirements" clearly points out the grid-connection technical requirements of the newly-built and expansion of wind farm, and adds the requirements of low voltage ride through capability of wind farms. The wind farm operators will have to increase by a large investment to meet the requirements; the "distributed access wind power project development and construction guidance" also proposed new technical requirements to the turbine unit replacement under distributed access wind power at low wind speed wind scene, which will directly result in an increase in the cost for low speed wind farm to do business dramatically.
It is said that the rebuilding of a 50,000 KW wind farm unit grid-connection takes at least one million yuan, let alone the difficulty in the technology of the distributed wind field rebuilding. It is expected that wind farm operators will be faced with a even greater increase in the costs.
NewEnergyLive is StanfordPoint new energy portal specializing in providing new and clean energy, bioenergy news, information, reports, market research and data analysis of China market. Its in-depth research, sophisticated data analysis and insightful consultancy are all based on robust and previously unavailable information on economy, financial and investment market as well as energy sources, prices and deals around the world.
Monday, February 27, 2012
The First High-Concentrating PV Generation System of the World Located in China Anhui Achieved Production Capacity
The ceremony of Sino-US joint venture Suncore Photovoltaic Technology Co., Ltd.'s high-concentrating photovoltaic industrialization project phase one put into production and phase two groundbreaking was held in Anhui Huainan, China's first hundred million ton coal base.
The first phase of the project put into operation marks that the world's first high-power concentrating photovoltaic power generation systems and automated production line of modules with an annual output of up to 200MW have achieved production capacity.
Suncore photovoltaic high-concentrating photovoltaic industrialization project has a total investment of RMB 8 billion yuan, covering an area of 1,600 mu, the total annual output of high-power concentrating photovoltaic power generation systems and modules is up to 1000MW. It will become the world's largest and most technologically advanced high power concentrator photovoltaic industry base.
It is reported that Concentrating Photovoltaic (CPV) system technology is the third generation of photovoltaic generation technology. Compared with other types of solar cells, it has the advantages of high photoelectric conversion efficiency, small footprint, short energy consumption recovery period, able to maximize the use of solar energy resources, so it is expected to. become the key technology for the sustainable development of future energy and environmental fields in a short term.
The high-concentrating photovoltaic power generation system and modules with the annual production capacity of 200MW are all operated by automatic robot assembly line.
Huainan is the largest "coal city" of East China with centuries of coal mining history, the first hundred million tons of coal base in China, with coal and other conventional energy sources dominating the city's economic structure. The aim of the construction of concentrating photovoltaic industry base is to create a three-dimensional energy city, and realize transformation and upgrading of the city.
The first phase of the project put into operation marks that the world's first high-power concentrating photovoltaic power generation systems and automated production line of modules with an annual output of up to 200MW have achieved production capacity.
Suncore photovoltaic high-concentrating photovoltaic industrialization project has a total investment of RMB 8 billion yuan, covering an area of 1,600 mu, the total annual output of high-power concentrating photovoltaic power generation systems and modules is up to 1000MW. It will become the world's largest and most technologically advanced high power concentrator photovoltaic industry base.
It is reported that Concentrating Photovoltaic (CPV) system technology is the third generation of photovoltaic generation technology. Compared with other types of solar cells, it has the advantages of high photoelectric conversion efficiency, small footprint, short energy consumption recovery period, able to maximize the use of solar energy resources, so it is expected to. become the key technology for the sustainable development of future energy and environmental fields in a short term.
The high-concentrating photovoltaic power generation system and modules with the annual production capacity of 200MW are all operated by automatic robot assembly line.
Huainan is the largest "coal city" of East China with centuries of coal mining history, the first hundred million tons of coal base in China, with coal and other conventional energy sources dominating the city's economic structure. The aim of the construction of concentrating photovoltaic industry base is to create a three-dimensional energy city, and realize transformation and upgrading of the city.
During The"12th Five Year" Period Investment on Biogas Projects in China May Exceed 20 Billion Yuan
It is heard from Ministry of Agriculture that the during the "12th Five-Year" period, the state will invest 20 billion yuan for the development of biogas projects, including rural biogas projects, the construction of large and medium biogas and biogas power generation, etc. Along with the progress of the project, the total investment may also increase.
The 12th Five-Year Plan on the development of modern agriculture just announced also required to organize and implement a number of key projects based on the key tasks mainly on the most urgent and most critical, the weakest links and areas of focus. Among the listed 14 major projects in the plan, "rural biogas project" is included in item 12. The planning requires "to speed up the construction of household biogas the farming community and associated household biogas as well as large and medium biogas projects, and to improve Biogas services and technology support system." The planning also pointed out to increase the farmers methane penetration rate from 33% in 2010 to more than 50%, average annual growth rate higher than 17%.
Currently nearly 300 enterprises are engaged in biogas engineering design, construction, equipment manufacturing, operation and management, employing nearly 10,000 staff, with enterprises total turnover of nearly 10 billion. However, it is said that the performance differences of the key equipment such as generators, purification towers, control system are large, with inconsistent quality and short life and the lack of industry standards and specifications of constraints, some projects do not operate normally due to the poor key equipment performance, which increases the difficulty and costs of the operation and management of post-projects.
It is suggested that relevant departments should cultivate industry leaders as the key link in the promotion of biogas projects, establish incentives and give full support to policy, funding, taxation, personnel training, technology, etc., and as soon as possible select a number of advanced new technologies and new products, prepare new technologies and new products catalogue, and guide the promotion departments and owners to make correct selections.
The 12th Five-Year Plan on the development of modern agriculture just announced also required to organize and implement a number of key projects based on the key tasks mainly on the most urgent and most critical, the weakest links and areas of focus. Among the listed 14 major projects in the plan, "rural biogas project" is included in item 12. The planning requires "to speed up the construction of household biogas the farming community and associated household biogas as well as large and medium biogas projects, and to improve Biogas services and technology support system." The planning also pointed out to increase the farmers methane penetration rate from 33% in 2010 to more than 50%, average annual growth rate higher than 17%.
Currently nearly 300 enterprises are engaged in biogas engineering design, construction, equipment manufacturing, operation and management, employing nearly 10,000 staff, with enterprises total turnover of nearly 10 billion. However, it is said that the performance differences of the key equipment such as generators, purification towers, control system are large, with inconsistent quality and short life and the lack of industry standards and specifications of constraints, some projects do not operate normally due to the poor key equipment performance, which increases the difficulty and costs of the operation and management of post-projects.
It is suggested that relevant departments should cultivate industry leaders as the key link in the promotion of biogas projects, establish incentives and give full support to policy, funding, taxation, personnel training, technology, etc., and as soon as possible select a number of advanced new technologies and new products, prepare new technologies and new products catalogue, and guide the promotion departments and owners to make correct selections.
Renewable Energy Riding High in China